Design and install a temporary air-supported structure (dome / bubble) including the installation of all HVAC units, duct work, backup generator units, interior lighting, revolving door, and air lock building entryways for vehicles.
Design consideration to affix anchor beam to top portion of box suites from Field 6 to permit additional spectator viewing.
Run electrical conduit from northwest section of indoor facility to field 5 with sufficient load capacity for outdoor LED lighting, special events (concerts) and temporary air-supported structure mechanisms including unit back-up generators.
Removal of existing pine trees adjacent to building and border of parking lot.
Resurface and grade site in accordance to master drainage plan.
Install French drain around perimeter of synthetic turf connected to the main facility drainage system, accommodating water runoff, including snow loads, when air-supported structure is operational.
Construct a code approved, elevated load bearing steel platform to meet and exceed repositioning the existing HVAC unit while accommodating new units, including backup generators for temporary air supported structure.
Reposition and elevate existing HVAC unit to accommodate concrete pedestrian walkway.
Construct a code approved, elevated load bearing steel platform to meet and exceed repositioning the existing HVAC unit while accommodating new units, including backup generators for temporary air supported structure.
Reposition and elevate existing HVAC unit to accommodate concrete pedestrian walkway.
Design and install a synthetic turf field with inlaid soccer lines for small-sided soccer fields (9v9 & 7v7) taking into consideration drainage must accommodate a temporary air-supported structure during winter months.